No.1/41/2009-1R(Vol.11)  Government of India  Ministry of Personnel, Public Grievances and Pensions  Department of Personnel & Training ...





No.1/41/2009-1R(Vol.11) 


Government of India 


Ministry of Personnel, Public Grievances and Pensions 


Department of Personnel & Training 





North Block, New Delhi-110001 


Dated:13.7.2012 


NOTICE 

In para 2.2 of the RFP(Vol.III) of the project "RTI Call Centre and Portal" it

has been mentioned that the Stabilization period shall be for the 3 months from

the date of Go Live. Service Levels shall be operational post Stabilization period

of the project. This clause of RFP has been reconsidered and it has been

decided by the competent authority to revise the Stabilization period to 6 months

instead of 3 months and the service levels shall be operational after the

stabilization period of the project

.


(Santa Nair) 


Under Secretary(IR)